Balingian Power Station624 MW Natural Gas

GasVerified: Feb 2026

The Balingian Power Station is a key gas-fired power generation facility located in Malaysia, with a capacity of 624 MW. Operated by Sarawak Energy, this power plant plays an important role in the energy landscape of Sarawak, contributing to the region's electricity supply and overall energy mix. The facility utilizes state-of-the-art natural gas technology, which is known for its efficiency and reduced emissions compared to coal-fired power generation. Located at coordinates 2.7375, 112.4746, the Balingian Power Station is strategically placed to support the local grid and meet the energy demands of both residential and commercial sectors. Malaysia has been actively promoting the use of natural gas as a primary energy source, and the Balingian Power Station aligns with national energy policies focused on sustainability and reducing reliance on fossil fuels. The plant's operational capacity significantly enhances energy security in the region, ensuring that the growing demand for electricity is met while also supporting Malaysia's commitment to achieving a cleaner energy future. By providing essential power generation, the Balingian Power Station serves as a vital asset in Sarawak's energy infrastructure, reflecting the country's ongoing transition towards more sustainable energy practices.

Capacity
624 MW
Commissioning Year
2015

11 years old

Owner
Sarawak Energy
Location
2.7375°, 112.4746°

Malaysia, Asia

Context & rankings
  • 43. largest of 157 plants in Malaysia
  • #3,893 worldwide by installed capacity
  • #1,371 of 5,146 Natural Gas plants worldwide
  • 0.78% of the installed capacity of Malaysia
Age & fleet comparison

11 years in operation

Natural Gas fleet average: 26.9 years

Operator portfolio

Sarawak Energy operates 25 plants totalling 12,872 MW

Regional density

6 plants within 100 km, 3,650 MW combined

Nearest plant: Mukah Coal power station (30.7 km)

Data provenance

Source: Wikidata

Location

Coordinates:: 2.737530, 112.474610
Open in Google Maps
Carbon Footprint490 g CO₂/kWh
Annual CO₂
1.21 Mt
2460 GWh/year × 490 g/kWh
Cumulative CO₂
13.26 Mt
Over 11 years of operation
Est. Retirement
2045
19 years remaining
Annual emissions equivalent to
262.0K
cars per year
160.7K
homes per year
54.8M
trees to offset

Estimates based on Gas emission factor (490 g CO₂/kWh) and capacity factor (45%). Actual emissions may vary based on operating conditions, efficiency, and fuel quality.

Technical Details

Primary Fuel Type
Gas
Energy Source
Non-Renewable
Country
Malaysia
Continent
Asia
Data Source
Global Power Plant Database

Balingian Power Station: A Key Player in Malaysia's Energy Landscape

Balingian Power Station, located in the Sarawak state of Malaysia, is a significant natural gas-fired power generation facility with a total installed capacity of 624 megawatts (MW). Owned and operated by Sarawak Energy, this power station plays a critical role in the energy sector of Malaysia, particularly in meeting the growing electricity demand within the region. Since its commissioning, Balingian Power Station has been instrumental in ensuring a stable and reliable power supply, contributing to the economic development and sustainability initiatives of Sarawak.

The Balingian Power Station utilizes natural gas as its primary fuel source, which is known for being a cleaner-burning fossil fuel compared to coal and oil. Natural gas combustion produces lower volumes of greenhouse gases and other pollutants such as sulfur dioxide (SO2) and particulate matter, making it a more environmentally friendly option for power generation. The facility employs advanced gas turbine technology that enhances efficiency and reduces emissions, aligning with Malaysia's commitment to sustainable energy practices and the reduction of carbon footprints.

In the context of Malaysia's energy landscape, Balingian Power Station is pivotal in diversifying the country’s energy mix. The Malaysian government has been actively working towards increasing the share of renewable energy sources in its power generation portfolio; however, natural gas remains a dominant fuel in the short to medium term. The capacity of 624 MW provided by Balingian significantly contributes to the state's overall power generation capabilities, helping to mitigate energy shortages and support industrial growth in Sarawak. Additionally, the power station's operation supports regional electrification efforts, improving access to electricity for rural and urban communities alike.

Despite its contributions to energy security, the environmental impact of natural gas extraction and usage must be considered. While natural gas is less polluting than other fossil fuels, the processes involved in its extraction, including hydraulic fracturing and methane leakage during transport, can pose significant environmental risks. Sarawak Energy has been proactive in implementing measures to minimize these impacts, including adopting best practices for emissions control and investing in carbon offset initiatives.

Regionally, Balingian Power Station stands as a cornerstone of Sarawak's energy infrastructure. It not only powers local industries and households but also supports the state's ambitions to become a hub for economic development in East Malaysia. The integration of this power plant within the broader energy framework of Malaysia highlights the importance of reliable energy sources in facilitating growth and advancing the nation’s strategic goals. As Malaysia continues to navigate the transition towards a more sustainable energy future, the role of Balingian Power Station exemplifies the balance between energy needs and environmental stewardship.

MalaysiaEnergy Profile

157
Total Plants
79.6 GW
Total Capacity
GasCoalHydroSolar
Top Fuels

See Incorrect or Missing Data?

Help us improve our database by reporting any corrections or updates. Your contribution helps keep our global power plant data accurate and up-to-date.